All prefabricated components and walking slabs shall be fully equipped and loaded in accordance with the specifications and quantity requirements of each bridge, then transported to the construction site. Materials shall be manually unloaded at appropriate positions at the bridge head, and brackets shall be installed by manual lever hoisting.
(1) Before bracket installation, clean dirt and impurities on the pre-embedded U-bolts at the beam edge, repair or replace damaged nuts, and chisel off protruding concrete at the bolt roots.
(2) Install brackets sequentially from one end of the beam to the other, and fasten double nuts in a timely manner.
(3) Prior to handrail installation, conduct a preliminary horizontal adjustment on the installed bracket columns to ensure the top elevations of columns are roughly consistent, so as to realize smooth connection between handrails and columns.